TIMELINE | ACTIVITY |
---|---|
MONTH 1 | ORIENTATION CAMP |
MONTH 2 | PLACEMENT OF CM ON CDS GROUPS AND SETTLING DOWN OF CORPS MEMBERS |
MONTH 3 | DEVELOPMENT AND SUBMISSION OF PROPOSALS |
MONTH 4 | DEVELOPMENT AND SUBMISSION OF PROPOSALS CONTINUED |
MONTH 5 | APPROVALS OF PROPOSALS AND PROJECT COMMENCEMENT |
MONTH 6 | SUPERVISION AND MONITORING OF PROJECTS BY RELEVANT OFFICERS |
MONTH 7 | COLLATION AND SUBMISSION OF QUARTERLY REPORTS
LATE SUBMISSION OF PROPOSALS AND APPROVALS |
MONTH 8 | CONTINUATION OF PROJECT EXECUTION AND SUPERVISION BY RELEVANT OFFICERS
LATE SUBMISSION OF PROPOSALS AND APPROVALS |
MONTH 9 | CONTINUATION OF PROJECT EXECUTION AND SUPERVISION BY RELEVANT OFFICERS |
MONTH 10 | FINAL REPORTS AND INAUGURATION OF PROJECT |
MONTH 11 | PASSING OUT |
Table of Content
- Foreward
- Preface
- PREAMBLE
- OBJECTIVES OF CDS
- CLASSIFICATION OF CDS
- IDENTIFICATION OF PROJECTS THROUGH NEEDS ASSESSMENT
- PROGRAMME OR PROJECT SELECTION
- STEPS FOR EXECUTION OF CDS PROJECT
- CRITERIA FOR CONSIDERATION OF CDS PROJECT FOR APPROVAL
- CDS GENERIC TIME LINE
- COMMUNITY ENTRY
- ACTIVITIES OF COMMUNITY ENTR
- STRATEGIES FOR MOBILISING FUNDS AND MATERIALS
- LINKAGES AND THEIR USEFULNESS
- FREQUENTLY ASKED QUESTIONS AND ANSWERS ON CDS
- CONCLUSION